Have you noticed? Change Requests are normally and primarily outputs of EXECUTING and MONITORING and CONTROLING processes.
There is one instance however where they go out of a planning proceess. Do you know which one?
With this simplifying trick, the following is the only trick you need to remember to know everything about Change Requests as outputs:
b | c | d
9 | 1, 5, 6(3/3), 9, 10 | All except PICC
As you can see, the only planning process is 9b: Plan Procurement Management. I simply gave it a friendly little term: "a change request anomaly".
There is one instance however where they go out of a planning proceess. Do you know which one?
With this simplifying trick, the following is the only trick you need to remember to know everything about Change Requests as outputs:
b | c | d
9 | 1, 5, 6(3/3), 9, 10 | All except PICC
As you can see, the only planning process is 9b: Plan Procurement Management. I simply gave it a friendly little term: "a change request anomaly".