EEF & OPA - into what processes do they go?

OK. Enterprise Environmental Factors and Organizational Process Assets  are frequent inputs. So frequent that sometimes they become a little bit intimidating. So let's make clear - visually - whrere they are and where you can simply forget about them.
These are frequent inputs. So frequent that sometimes it becomes a little bit intimidating especially when you just read it. So let's make it clear - visually - whrere they are and where you can simply forget about them.



The following is done based on  <<Simplified Processes Matrix>> by knowledge area.
1 - All have both except Close Project/Phase -> OPA
2 - Plan Sco Mngt & WBS -> both; Define Scope & Control Scope -> OPA; Collect Requirements & Validate Scope -> neither
3 - All have both, except Control Schedule that has neither
4 - Plan Cost Mngt & Estimate Costs have both; Determine Budget has OPA; otherwise neither
5 - Plan QM -> both; Assurance -> neither; Control Quality -> OPA
6 - Plan HR & Acquire PT -> both; Develop PT -> neither; Manage PT -> OPA
7 - Plan Comm & Manage Comm -> both; Control Comm -> OPA
8 - All have both except Plan Risk Responses & Control Risks -> neither
9 - Plan Procurement M -> both; Conduct Procurements -> OPA; rest has neither
10 - Identify Stakeholders & Plan St Mngt -> both; Mng Stakeholder Engagement -> OPA; Control Sta Eng -> neither
In other words
--------
BOTH are in:
(First just remember that all Initiating and "Plan ... Mngt" ones have both)
up until now it's easy :)
then it's slightly more complicated
2 - Plan Sco Mngt & WBS
3 - All except Control Schedule
4 - Plan C Mngt & Estimate Costs
5 - Plan Q Mngt
6 - Plan HR Mngt & Acquire PT
7 - Plan Comm & Manage Comm
8 - Plan Risk Mngt & Identify Risks
9 - Plan Procurement Mngt
10 - Identify Stak & Plan Stak Mngt
OPA is in:
1 - Close Project or Phase
2 - Define Scope, Control Scope
5 - Control Quality
6 - Manage Pr Team
7 - Control Comm
9 - Conduct Procurements
10 - Manage Stak Engagement
Neither is in:
-
2 - Collect Requirements & Validate Scope
3 - Control Schedule
4 - Determine Budget
5 - Quality Assurance
6 - Develop Pr Team
-
8 - Plan Risk Resp, Control Risk
9 - Control Procurements & Close Procurements
10 - Control Sta Engagement